Fort Island Trail Septic Remediation Project
Fort Island Trail Septic Remediation Estimated Project Updates
Dixie Shores
West Bayshore Drive - Crew has been working on passing the pressure test required by the County. They are having to go back and redig some of the connections as they find leaks in the system. When this is complete and passed, they will start on site restoration and sodding.
West Sunnybrook Court - Services have been completed and crew is cleaning up the area. Pressure testing should start next week, waiting on Bayshore to pass.
West Coquina Court - Services have been completed and crew is cleaning up area.
Crystal Shores
North Watersedge Drive - Drilling started for the main line of the force main from Pinebark Ln. heading west to the end of Watersedge Drive. Sewer lateral installations under roadways have been ongoing from the west end of Watersedge to Pilot Pt.
North Pilot Point - No work scheduled for this week.
Fort Island Trail Septic Remediation Estimated Project Plans
Sheet #05: West Coquina Court
Sheet #06: West Sunnybrook Court
Sheet #07: West Bayshore Drive
Sheet #08: West Bayshore Drive
Sheet #10: North Watersedge Drive
Sheet #11: North Watersedge Drive
Sheet #12: North Pilot Point