Fort Island Trail Septic Remediation Project

FITSRP-Pg-Cover



Fort Island Trail Septic Remediation Estimated Project Schedule
12/13/2023 01/22/2024 West Bayshore Drive
01/23/2024 02/09/2024 West Sunnybrook Court
02/12/2024 02/26/2024 West Coquina Court
02/27/2024 03/07/2024 West Dixie Shore Drive
03/08/2024 04/11/2024 North Watersedge Drive
04/12/2024 04/20/2024 North Pilot Point
04/23/2024 04/30/2024 Complete Tie-ins and Testing
05/01/2024 05/13/2024 Final Inspections
05/14/2024 07/03/2024 DEP Clearance and Release

Sheet #05: West Coquina Court
FITS-001-web
Sheet #06: West Sunnybrook Court
Ft-Island-Trail-Septic-Remediation-drawings Page 002
Sheet #07: West Bayshore Drive
Ft-Island-Trail-Septic-Remediation-drawings Page 003

Sheet #08: West Bayshore Drive
Ft-Island-Trail-Septic-Remediation-drawings Page 004

Sheet #10: North Watersedge Drive
Ft-Island-Trail-Septic-Remediation-drawings Page 005
Sheet #11: North Watersedge Drive
Ft-Island-Trail-Septic-Remediation-drawings Page 006
Sheet #12: North Pilot Point
Ft-Island-Trail-Septic-Remediation-drawings Page 007